Assignment
Name: Emergency Rehabilitation Works of
Cyclone-AILA Damages in 4 Polders of Khulna and Satkhira Districts, financed
by ADB Loan No. 2200 BAN (SF), Grant No. 0036-BAN |
Country: |
|
Assignment
Location within Country: |
Duration
of assignment (months): 18 |
|
Name of Client: |
Professional
Staff Provided by our Organization: No.
of Staff: 08 No.
of Person-Months: 80 |
|
Start
Date (Month/Year): January 2010 |
Completion
Date (Month/Year): December
2011 |
|
Name
of Associated Consultants, if any: Resource
Planning and Management Consultants (Pvt.) Ltd |
No.
of Person-Months of Professional Staff Provided by Associated Consultants: 36 |
|
Name
of Senior Staff (Project Director/Coordinator, Team Leader) Involved and
Functions Performed: 1.
AHM Mahbubur Rahman,
Team Leader 2.
AKM Badruddoza, Team Leader/Procurement Specialist 3.
ANM Wahedul Huq, Sr.
Design Engineer. 4.
Mohiruddin Ahmed,
Design Engineer. |
||
Detailed
Narrative Description of the Project: The
coastal polders of the South-western Area of Bangladesh was severely damaged
by the Cyclone-AILA of On appeal of the Bangladesh Water Development Board,
ADB agreed to grant loan for the rehabilitation work of these damages. BWDB
has been assigned the responsibility to rehabilitate the damaged
infrastructures and so the consultant is engaged for design, supervision and
monitoring the construction works of
the rehabilitation activities in 4
polders. |
||
Detailed
Description of Actual Services Provided by our Staff: The consultant provided the following services: ·
Review & update the damage assessment
already prepared by the Executing Agency; ·
Detailed design of the damaged structures; ·
Assist in preparation and evaluation of
tender; ·
Supervision & quality control of
construction works, certification of contractors bill for payment; ·
Assessment of impact on environment; ·
Project management and monitoring. |
||
Firm’s
Name:
Design Planning & Management Consultants Ltd.