   Assignment
  Name: Additional Drainage Study to determine a
  sustainable solution for the drainage problems in the Baggar Dona River
  Catchments Area under CDSP-III.  | 
  
   Country:    | 
 |
| 
   Assignment
  Location within Country: Noakhali District  | 
  
   Duration
  of assignment (months): 12  | 
 |
| 
   Name of Client:  BWDB  | 
  
   Professional
  Staff Provided by our Organization:  No.
  of Staff: 3 No.
  of Person-Months: 10   | 
 |
| 
   Start
  Date (Month/Year): May 2008  | 
  
   Completion
  Date (Month/Year): April
  2009  | 
  
   Approx.
  value of Service: Tk. 8.118 Million  | 
 
| 
   Name
  of Associated Consultants, if any:   Kranti Associates Ltd. Sheltech Consultants (Pvt.) Ltd. &  IWM  | 
  
   No.
  of Person-Months of Professional Staff Provided by Associated Consultants: 44  | 
 |
| 
   Name
  of Senior Staff (Project Director/Coordinator, Team Leader) Involved and
  Functions Performed: Mr. Mohiruddin Ahmed : Design Engineer   | 
 ||
| 
   Detailed
  Narrative Description of the Project: Main objective of the study is to recommend an
  appropriate solution for the drainage problem of the catchment areas of the   | 
 ||
| 
   Detailed
  Description of Actual Services Provided by our Staff: Preparation
  of sustainable drainage plan, design & probable cost estimate,
  implementation plan considering technical, socio-economic and environmental
  aspects, economic analysis and EIRR of the project, preparation of the basic
  project information in GIS map, GIS based database and submission of reports.  | 
 ||
Firm’s
Name:
Design Planning & Management Consultants Ltd.