Assignment
Name: Design
and Supervision consultancy of 21 nos. bridges at different Upazilas
of Barisal, Perojpur, Bhola & Jhalokathi Districts under GBDRCHBIDP |
Country: |
|
Assignment
Location within Country: |
Duration
of assignment (months): 48 |
|
Name of Client: Local
Government Engineering Department (LGED) |
Professional
Staff Provided by our Organization: No.
of Staff: 6 No.
of Person-Months: 131 |
|
Start
Date (Month/Year): May 2010 |
Completion
Date (Month/Year): April
2014 |
|
Name
of Associated Consultants, if any: Kranti
Associates Ltd. |
No.
of Person-Months of Professional Staff Provided by Associated Consultants: 164 |
|
Name
of Senior Staff (Project Director/Coordinator, Team Leader) Involved and
Functions Performed: Anwar Ahmed : Team Leader |
||
Detailed
Narrative Description of the Project: The project will be implemented in |
||
Detailed
Description of Actual Services Provided by our Staff: Hydrological and morphological study for 11 nos.
bridges, detail survey (geometric
& plan table), prepare land acquisition plan, conduct hydrological study
with necessary data collection, sub-soil investigation, topographical survey,
fix up the length of the bridge and cost effective design in consideration of
hydrological and morphological study report, plan, structural design &
drawing including bar bending schedule, detail engineering estimate and Bill
of Quantities, plan, design & estimate of approach road and full time
supervision of construction works. |
||
Firm’s
Name:
Design Planning & Management Consultants Ltd.